Snubbing Case History #36

Objective: Move tubing up hole 300m

Well Information: 9 Mpa, 1.5% H2S gas well.

Procedure: Rig up snubbing unit and pressure test. Strip out tubing hanger, and 30 joints tubing. Strip in tubing hanger, set packer land tubing and rig out snubbing unit.

Time on location: 7 hours