Snubbing Case History #37
Objective: Drill into productive zone, install completion
Well Information: 4,500 Kpa gas well 700m deep
Procedure: Rig up snubbing unit and pressure test. POOH production tubing. RIH bit, motor, floats, and tubing to bottom. Drill down to required depth. POOH same. RIH production tubing. Rig out snubbing unit.
Time on location: 19.3 hours