Snubbing Case History #33

Objective: Pull production tubing, perforate new zone and re-install w/ packer.

Well Information: 6 Mpa gas well, 900m deep.

Procedure: Rig up snubbing unit and pressure test. Strip out tubing hanger and tubing. Rig out snubbing unit to perforate. Rig up snubbing unit and pressure test. Strip in BHA and 900m tubing, strip in tubing hanger, set packer, land tubing and rig out snubbing unit.

Time on location: 15 hours.