International Snubbing Case History #6

Objective: Snub in tandem packer completion string with seal assembly.

Well Information: 12,400 kPa, 3100 meters, 3 zones gas well.

Procedure: Snub in chrome tubing with tandem packer, seal assembly and expansion joint. Sting into permanent packer, space out using expansion joint, set hydraulic set packers and land tubing hanger. Rig out rig assist snubbing unit.

Time on location: 20 hours over 2 days.