International Snubbing Case History #5
Objective: Snub in completion string after pin point frac.
Well Information: 2800 meters, 11,300kPa and 3 zones.
Procedure: Rig up 5K Class 3 BOP stack and self-contained snubbing unit on a 10K 4 1/16” valve. Snub in BHA consisting of seal assembly, 2 hydraulic set packers, assorted nipples and sliding sleeves and blast joints along with premium chrome tubing. Sting into permanent packer, space out and set hydraulic set packers. Rig out snubbing unit.
Time on location: 34 hours over 3 days