Snubbing Case History #25
Objective: Retrieve bridge plug and install completion tubing.
Well Information: 13 Mpa sweet gas well, 2,350m deep
Procedure: Rig up snubbing unit and pressure test. Strip out tubing hanger and run in 3 joints to tag sand. Pull wireline plug and wash clean onto bridge plug and release. Set wireline plug and POOH tubing and BHA. RIH re-entry guide, pup, profile with plug in place, pup, and tubing. Tag fill. Pull wireline plug and clean out cellar. Set plug and pull 4 joints, strip in tubing hanger and land tubing. Rig out snubbing unit.
Time on location: 22.5 hours