Snubbing Case History #18

Objective: Install dual zone completion.

Well Information: 3,500 Kpa gas well, 450m, two zones

Procedure: Pick up snubbing unit, place on rig BOPs, split stack above rams, install spool to house packer, and pressure test. RIH re-entry guide, pup, profile with plug in place, pup, and 4 joints. Strip in packer, pup, blast joints, pup, port sub, pup, and 43 joints. Strip in tubing hanger, set packer, land tubing and rig out snubbing unit and spools.

Time on location: 6 hours