Snubbing Case History #10
Objective: Retrieve bridge plug and install production tubing.
Well Information: 5,500 Kpa sweet gas well, 800m deep.
Procedure: Rig up snubbing unit and pressure test. RIH retrieving skirt, pup profile with plug in place, pup and 79 joints. Latch onto bridge plug and release. POOH same. RIH tubing end plug, 1 joint, profile, pup, and 76 joints. Strip in tubing hanger and land tubing. Rig out snubbing unit.
Time on location: 7 hours