![]() |
Ph: (780) 955-3550 TF: 1-888-476-8226 |
![]() |
||||||||||||||||
|
||||||||||||||||||
|
|
![]() |
|
Case History 1
Time on location: 4 hours per well.
Case History 2
Time on location: 6.5 hours
Case History 3
Time on location: 8.5 hours
Case History 4
Time on location: 13 hours
Case History 5
Time on location: 9.5 hours
Case History 6
Objective: Land velocity stringWell information: 9200kPa, sweet gas, 2100 metersProcedure: Rig up CT unit with spooler and pressure test. RIH and land at predetermined depth. Isolate well bore pressure and cut and land coil. Rig out.Time on location: 9.5 hours
Case History 7
Objective: Pump nitrogen blanketWell information:Procedure: Rig up nitrogen unit and pressure test. Pump hole volume into well to hold down H2S. Rig out unit.Time on location: 1.5 hours
Case History 8
Time on location: 10.5 hours
Case History 9
Time on location: 5.5 hours
Case History 10
Time on location: 13 days
Case History 11
Time on location: 6 hours
Case History 12
Time on location: 1 hour
Case History 13
Time on location: 4 hours total to pump on both wells
.Case History 14
Time on location: 13 hours. Pigs into catcher after 72 hours
Case History 15
Objective: Utilize Mayperf drilling tool to perforate multiple zones in a well.Well information:Procedure: Rig up and deploy Mayperf drilling tool utilizing 33 meters of lubricator. A total of 5 sets of perforations were opened up using the Mayperf drilling tool and 50.8mm coil tubing.Time on location: 30 hours over 3 days
Case History 16
Objective: Recover 3600m braided wireline / perforating BHA, and tractorWell Information: 14mpa WHP, sweet gas, 4000m with 1400m horizontal section, 114mm casing to PBTD, perforating tool stuck at 3600m, wireline had parted at surface and fell down hole.Procedure: MIRU 50.8mm coil tubing unit with injector extension hoses to accommodate 22m of lubricator required for tool recovery. Rig Injector, lubricator, and coil tubing BOP on to wireline BOP, and pressure test. Run in hole with “spear” fishing assembly to hook wireline and bring to surface. Once back at surface, secure wireline with BOPs, and strip off coil lubricator to expose wireline. Feed wireline through packoff, and strip additional cable through packoff using crane, causing cable to shear off cable head down hole. Once enough cable has been exposed, secure to wireline truck and spool on to drum. Repeat procedure as required until all wireline has been removed from well. Once wireline is out of well, rig on with coil and “overshot” fishing assembly and using jars, dislodge and recover perforating tool string and tractor.Results – Job completed successfully. Total trips in hole 7 – 5 to recover wireline, 1 impression block run, and 1 run to recover tool string. Job spanned 3 days utilizing 24 hour operations. After fishing operations were concluded, the remaining plugs were set, and perforations shot without further incident using Snubco coil tubing.
Case History 17 Objective – Remove scale buildup on tubulars – 2 wells on same pad Well Information – 7-10mpa WHP, Sweet gas, 4200m with 1100m horizontal section, 114mm casing to PBTD. Casing was plugged, and a camera run indicated that scale buildup was the problem. Procedure – MIRU 50.8mm coil tubing with 70mpa BOP. Rig up and pressure test. Run in hole pumping water until obstruction is tagged. Once depths and string weight have been confirmed, alternate slugs of 15% HCL acid and water, and work coil to bottom. Once at bottom, perform acid wash to heel, then cleanout run back to bottom and unload well with nitrogen. Results – PBTD reached on both wells in 48 hours utilizing 24 hour crews. |
||||||||||||||
|
© Copyright Snubco Pressure Control Ltd. Terms & Conditions | Employee Email | Design by Primal Tribe | Site Map | Log In |